News

Actions

First Warning Traffic – Monday bridge opening and tunnel closures for this week

Posted at 8:55 AM, Dec 04, 2017
and last updated 2017-12-04 08:55:46-05

BRIDGE OPENING

James River Bridge 10:30 AM

ELIZABETH RIVER TUNNELS WEEKLY  SCHEDULE Friday, December 1 to Friday, December 8
Below is a list of tunnel/lane closures for the Elizabeth River Tunnels. All work is dependent upon weather conditions and closure dates are subject to change.

DOWNTOWN TUNNEL:

I-264 East Downtown Tunnel: Alternating lane closures in the Downtown Tunnel eastbound on Sunday, December 3 from 6 a.m. until 10 a.m.
I-264 West Downtown Tunnel: Alternating lane closures in the Downtown Tunnel westbound on Sunday, December 3 from 6 a.m. until 10 a.m.
I-264 East Downtown Tunnel: Alternating lane closures in the Downtown Tunnel eastbound on Sunday, December 3 from 8 p.m. until 5 a.m. the following morning.
I-264 West Downtown Tunnel: Alternating lane closures in the Downtown Tunnel westbound on Monday, December 4 and Tuesday, December 5 from 8 p.m. until 5 a.m. the following morning.

MIDTOWN TUNNEL: 
US 58 East Midtown Tunnel: Alternating lane closures in the Midtown Tunnel eastbound on Sunday, December 3 from 6 a.m. until 10 a.m.
US 58 West Midtown Tunnel: Alternating lane closures in the Midtown Tunnel westbound on Sunday, December 3 from 6 a.m. until 10 a.m.
US 58 West Midtown Tunnel: Right lane closure in the Midtown Tunnel westbound on Wednesday, December 6 and Thursday, December 7 from 8 p.m. until 5 a.m. the following morning.

FULL RAMP CLOSURES SCHEDULED FOR I-64 WIDENING PROJECT

Detours will be in place during overnight closures on December 3-7

NEWPORT NEWS — Contractor crews with the Virginia Department of Transportation (VDOT) will close the following ramps to perform construction activities on the second segment of the I-64 Widening Project:

December 3-7:

  • I-64 west off-ramp to Route 143 (exit 243B) as early as 7 p.m. to 5 a.m.
  • I-64 east on- and off-ramps at Route 199 west (exit 242A) as early as 8 p.m. to 5 a.m.
  • I-64 west on-ramp from Route 199 east as early as 7 p.m. to 5 a.m.

All construction work is dependent upon weather conditions. Signs will be in place to alert motorists to the ramp closures and detour.

 Additional scheduled lane closures for the I-64 Widening project this week include:

Segment II: Route 199 (exit 242) to Yorktown Road (exit 247)

  • Alternating single-lane closures on I-64 east and west from Colonial Parkway to Lee Hall (Exit 247) December 3-7, starting as early as 7 p.m. until 5 a.m.
  • Lane closures under flagger control on Penniman Road at the I-64 overpasses on December 3-7, from 8 p.m. until 6 a.m. the following morning.

Traffic will be detoured as follows:

I-64 west off-ramp to Route 143 (exit 243B) closure:

  • Take Exit 242A to Humelsine Parkway (VA-199 west)
  • Keep right and follow signs for VA-143 detour
  • Exit right at the Williamsburg VA-143 exit

I-64 east (exit 242A) ramp closure:

  • Take Exit 243B to Route 143 west
  • Follow signs on Route 143 west to ramp for Route 199 west

Route 199 east on-ramp to I-64 west closure:

  • Follow signs on Route 199 east to traffic signal
  • Make a U-turn at signal to access Route 199 west
  • Follow Route 199 west to I-64 west on-ramp

Route 199 west on-ramp to I-64 east closure:

  • Follow signs on Route 199 west to Route 60 ramp
  • From Route 60 take the Route 199 east ramp
  • Follow signs to the I-64 east on-ramp