News

Actions

First Warning Traffic – Monday Traffic Alerts

Posted at 6:11 AM, Sep 12, 2016
and last updated 2016-09-12 08:42:41-04

BRIDGE OPENINGS:

Gilmerton Bridge 9:00 AM, Noon, 3:00 PM and 7:00 PM – M-F Daily – 9:00 AM & 3:00 PM Saturday and Sunday

*

ERT WEEKLY CONSTRUCTION SCHEDULE From Friday, Sept. 9 to Friday, Sept. 16

 Below is a list of significant tunnel/lane closures for the Elizabeth River Tunnels (ERT) Project. Due to the nature of construction, closure dates are subject to change. Visit our Travel Impacts page for current information and a more detailed listing of long-term temporary road closures.

U.S. 58 East: Full weekend tunnel closure from Friday, Sept. 16 at 8 p.m. through Monday, Sept. 19 at 5 a.m.

London Boulevard East/ U.S. 58: Full on-ramp closure continues through Thursday, Sept. 15 from 7 p.m. each night until 5 a.m. the following morning. Additionally, this ramp will be closed on Saturday, Sept. 10 from 9 a.m. until 3 p.m.

I-264 East/ Frederick Boulevard: Full off-ramp closure  Sunday through Friday, Sept. 11-16 from 7 p.m. each night until 5 a.m. the following morning.

I-264 East/West: Alternating lane closures between Effingham Street and Victory Boulevard Sunday through Friday, Sept. 11-16 from 7 p.m. each night until 5 a.m. the following morning.

*

HAMPTON ROADS WEEKLY LANE CLOSURES REPORT September 9, 2016 through September 16, 2016

  • I-64 Hampton Roads Bridge-Tunnel: Single-lane closures westbound. One lane will remain open at all times:
  • Westbound September 11-15 from 9 p.m. until as late as 5 a.m. the following morning.
  • I-664 Monitor-Merrimac Memorial Bridge-Tunnel: Alternating and single-lane closures northbound and southbound as follows. One lane will remain open at all times:
  • Northbound September 13-15 from 10 a.m. until 2 p.m.
  • Northbound September 13 from 8 p.m. until 5 a.m. the following morning.
  • Southbound September 14-15 from 9 p.m. until 5 a.m. the following morning.

 

  • US-17 James River Bridge: Night-time single-lane closures southbound and northbound. One lane will remain open at all times:
    • Southbound September 12-16 from 9 a.m. until 3 p.m.
    • Northbound September 16 from 9 a.m. until 3 p.m.
  • I-64 High Rise Bridge: Single-lane closures as follows eastbound and westbound. One lane will remain open at all times:
  • Eastbound September 11 from 4 a.m. until 9 a.m. the following morning.
  • Eastbound /Westbound September 12-15 from 8 p.m. until 5 a.m. the following morning.
  • US-17 George P. Coleman Bridge: Single-lane closures as follows eastbound and westbound. One lane will remain open at all times:
  • Northbound September 12-16 from 9 a.m. until 3 p.m.
  • Terminal Boulevard Resurfacing, Norfolk: Full weeknight/weekend closures westbound as follows. Alternating lane closures eastbound as follows and one lane will remain open at all times:
    • Eastbound September 12-16 from 9 a.m. until 3 p.m.
  • Westbound Weeknights September 12-16 from 8 p.m. until 5 a.m. the following morning.
  • I-664 Southbound, Newport News: Single-lane ramp closures as follows southbound. One lane will remain open at all times. The Inspection Station will remain open at all times:
  • 23rd Street ramp to Terminal Avenue September 14-17 from as early as 7 p.m. until as late as 8 a.m. the following morning.
  • I-664 Northbound, Newport News: Single-lane closures as follows northbound. One lane will remain open at all times. The Inspection Station will remain open at all times:
    • I-664 Northbound to 25th Street Overpass September 14-15 from 8 p.m. until 5 a.m. the following morning.
  • I-464 Southbound, Chesapeake: Single-lane on-ramp closures September 12 from I-464 southbound to Route 17 (Elizabeth City exit) from 8:30 p.m. until 12 a.m. Intermittent traffic stoppages September 12 to begin at 10 p.m. and will last up to 15 minutes at a time. I-464 southbound (Oak Grove Connector) will not be impacted.
  • I-64 Eastbound, Hampton: Double-lane closures as follows eastbound. One lane will remain open at all times:
    • September 11-15 from 10 p.m. until 5 a.m. the following morning between I-664 Exit and Hampton River Bridge Overpass.
  • I-64 Westbound, Hampton: Single-lane closures as follows westbound. Two lanes will remain open at all times:
    • September 11-14 from 8 p.m. until 5 a.m. the following morning between Mercury Boulevard South and Mercury Boulevard North.
  • I-564 Eastbound, Norfolk: Single- lane closures eastbound September 12-15 from 7 p.m. until 5 a.m. the following morning between Terminal Boulevard and Norfolk Naval Station Gates 3A and 3.
  • I-564 Westbound Tunnel, Norfolk: Single- lane closures westbound September 14 from 2:30 p.m. until 6:30 p.m.

 

  • Military Highway Continuous Flow Intersection, Norfolk: Alternating single-lane closures as follows. One lane will remain open at all times:
  • September 11 – September 17: Single-lane closures northbound from 9 a.m. to 3 p.m. and from 7 p.m. until 5 a.m. the following morning on Military Highway between Lowery Rd and the intersection Military Highway/Princess Anne Road.
  • September 11 – September 17: Alternating single-lane closures eastbound and westbound from 7 p.m. until 5 a.m. the following morning on Princess Anne Rd between Cowand Avenue and the intersection of Military Highway.

 

  • I-95 Northbound/Southbound, Greenville County: Alternating lane closures northbound and southbound as follows. One lane will remain open at all times:
    • Southbound September 12-13 from 9 a.m. until 2:30 p.m. between Exit 17 and Exit 20.
    • Northbound September 14-15 from 9 a.m. until 2:30 p.m. between Exit 17 Exit 20.
  • US-17, Isle of Wight County: Single-lane closures southbound in Carrolton. One lane will remain open at all times:
    • September 12-16 from 9 a.m. until 3 p.m.
  • US-17 Sidney B. Hazelwood Bridge, Isle of Wight County: Alternating lane closures southbound and northbound. One lane will remain open at all times:
    • September 13-16 from 9 a.m. until 3 p.m.
  • Business Route 258, Cypress Creek Bridge, Smithfield: Alternating lane closures eastbound and westbound on Business Route 258. One lane will remain open at all times:
    • September 13-16 from 9 a.m. until 3 p.m.
  • US-60 Eastbound/Westbound, James City County: Consecutive single-lane closures eastbound and westbound September 7-16 from 7 a.m. until 7 p.m. between Forge Road and Industrial Boulevard. One lane will remain open at all times.
  • US-13 (Lankford Highway), Accomack County: Consecutive single-lane closures northbound at the intersection on Route 179. One lane will remain open at all times:
    • September 6-December 5 from 12 p.m. until 5 a.m. the following morning.

 

  • US-13 (Lankford Highway), Northampton County/Melfa: Daytime single-lane closures northbound and southbound in Onley. One lane will remain open at all times:
    • September 12-15 from as early as 7 a.m. until as late as 7 p.m.
    • September 15 from 6 a.m. until 6 p.m. (Melfa)
    • September 16 from as early as 7 a.m. until 12 p.m.
  • Elizabeth River Tunnels/Martin Luther King, Jr. Freeway:  Please check Elizabeth River Tunnels website for the latest closure and detour information regarding the Downtown Tunnel, Midtown Tunnel and the MLK Freeway.

 

 

  • George Washington Memorial Highway (Route 17), York County: Crews are widening the road between Route 630 (Wolf Trap Road) and Route 706 (Hampton Highway). Daytime single-lane closures, from 9 a.m.to 3 p.m. and weeknight single-lane closures, from 7 p.m. to 5 a.m. Expect traffic shifts and delays. For more about this project, please visit the Route 17 Widening website.

*

CHESAPEAKE:

NORTH BATTLEFIELD BLVD SINGLE LANE CLOSURE

Southbound North Battlefield Blvd right-turn lane at Medical Pkwy

Through October 15

 Continued utilities installation will keep the right-turn lane on southbound North Battlefield Blvd at Medical Pkwy closed through October 15.  Motorists should be alert to work crews, equipment in the area and possible delays.

*

VIRGINIA BEACH: Road Work on Indian River Road Started Monday the 15th

Virginia Beach Public Works has announced a roadway improvements project on Indian River Road will begin Monday, August 15, 2016.  The project will begin at Speed Fentress Bridge and Indian River Road to North Landing Road, and will include milling, paving and pavement marking work.

Crews will be working in the evenings from 7 p.m. until 5 a.m.  If any daytime work is needed, it will take place from 9 a.m. to 3 p.m.  If any weekend work is needed, the work hours will be from 7 a.m. until 5 p.m.

The project is scheduled to be completed by September 1, 2016.

Indian River Paving

*

NORFOLK: Military Highway Continuous Flow Intersection work northbound and southbound. Two lanes will remain open at all times.